RESIDENTIAL SERVICE REQUIREMENTS

CHAPTER 5 - METER REQUIREMENTS


GENERAL REQUIREMENTSFIGR23.GIF (6512 bytes)
This chapter provides you with general requirements for the metering equipment that you need in order to have your service energized. Your meter base needs to meet the following criteria for our meter to properly connect.

Your meter base and other equipment installation must meet the requirements of your local electrical inspector. If you have specific questions regarding your meter installation please contact your local electric inspection agency (see list).

Back to Contents

 

 

SERVICE RATING OPTIONS
As stated in Chapter One, CLPUD’s metering equipment requirements for single-family residential structures (not apartments or condominiums) are based upon the following single-phase service ratings [and the customer must select which amperage rating is required for the project]:

Ampere Rating Voltage
200 Amp 120/240
400 Amp 120/240
over 400 Amps* 120/240
* If you need a service over 400 amps or a three phase service, please contact your nearest service office (see appendix). Those services will be addressed individually and are not covered in this handbook.

You are responsible for providing and installing all equipment other than:FIGR24.GIF (13892 bytes)

Back to Contents

 

 

METER BASE REQUIREMENTS
The meter base you purchase and install shall meet the following general requirements. Specific requirements for 200 and 400 amp services, and for outbuildings, are listed later in this chapter.

Your meter base must be:

Back to Contents

 

 

200 AMP SERVICES
The 120/240 volt, 200 ampere service is the most common service installed by CLPUD. Typically it’s installed in homes with a living area of less than 2500 square feet. However, depending upon what type of equipment you are installing you may want a larger service. It is your responsibility to determine your electrical requirements and to notify CLPUD of the size of service you would like.

Meter bases for 200 amp services shall also:

The center knockout should not be used on underground because of the bending radius of the cable.

If your outbuilding or ancillary service will be used for commercial purposes (i.e. a professional shop, dairy barn, illuminated sign, multifamily/community well) you will have additional requirements. If this is the case please refer to the CLPUD Electric Service Handbook for Non-Residential Services.

Back to Contents

 

 

GROUNDING REQUIREMENTS
All meter bases and conduit shall be bonded and grounded in accordance with the NEC. Beginning in 1996, new construction shall have a "UFER" ground installation poured in the footings and be inspected by the building official. It is your responsibility to coordinate this installation with the proper authorities and receive their approval.

Back to Contents

 

 

CLEARANCE REQUIREMENTS
The following clearances are required around all meter installations. It is your responsibility to provide and maintain these clearances.

Back to Contents

 

 

400 AMP SERVICES
The meter base required for a 120/240 volt, 400 ampere service is called a "Class 320" meter base (see Figure 26). It is larger than the 200 amp meter base, but it is still a self-contained meter base (it doesn’t require instrument transformers). It can be installed on residences where the continuous current rating is 320 amps or less. If your structure will require more than 320 amps continuous, you are required to install an instrument transformer (CT or PT) service.

Class 320 meter bases for 400 amp services shall, in addition to the meter base requirements listed in this Chapter;

Back to Contents

 

 

400 AMP CT SERVICE
CT services are also known as "instrument transformers". You may request a 120/240 volt, 400 amp CT service, available at an additional charge. This service requires a different meter base (see Figure 27). It also requires additional equipment (CT enclosure, conduit, CT mounting bracket, etc.). Contact our nearest service office (see Offices) and ask to speak to the meter department.FIGR27.GIF (5654 bytes)

Phase Service
Amperage
CT’s Dimensions
No. of Transf. W H D
1 401-800A 2 24" 24" 11"’
3 201-400A 3 36" 36" 11"

Back to Contents

 

 

SERVICES OVER 400 AMPS
120/240 volt services over 400 amps require CT metering. Please contact your nearest service office (see Offices) for more information and ask to speak to the meter department.